Work continues on the house. Real Builders was in and measured for the beams to go in. They are ordered and should be going in soon, hopefully this week. They will also rebuild another load bearing wall and reposition a doorway in that wall. We have connected with All Points Construction. Once the beams are in and walls are removed in the basement All Points will pour the concrete. Either just before or after it dries for a few days they will also power wash the basement and treat it with a mold inhibitor. All Points have some people from Idaho and some local. They appear to be very knowledgeable and have all the proper credentials. They are working on 5 or 6 houses in Eastwood Park. One is our neighbor to the north. All Points is rebuilding their basement and front porch. We will probably use them to replace our back door and after we have electric, to also replace the kitchen floor and install cabinets.
The quest for an electrician continues.......
michael kors outlet
ReplyDeletecoach outlet online
christian louboutin shoes
tory burch outlet
christian louboutin sale
canada goose sale
ray ban glasses
canada goose outlet
the north face jackets
nike roshe run 3
2017.2.13chenlixiang