Progress was made yesterday. Real Builders finished the installation of the new beams to replace 2 of the load bearing walls. They also rebuilt another load bearing wall. Thanks to Joel Feist, Kenny Aberle and the others who came to our rescue in a short period of time and did the work. The main floor is now much more level as they raised it about 1 1/2 inches in the center of the house.
I met with the guy from the company putting in our new heating and A/C. He was fun to talk with and I believe Blaine knows his stuff. Today I am tearing out all the old duct work. The new system will be built from scratch. He says it will be about a week long job.
Electricians should be starting on Monday..... Greg Baumgartner (Trading Post Wrecking Yard) removed the motor home yesterday afternoon. The big rolloff dumpster will be removed this weekend or Monday morning. The house will begin to look a little less like the construction zone that it is.
No comments:
Post a Comment