Friday, November 11, 2011

Evacuated - Day 142 - Nov 11, 2011

Today the texturing shoould be done on the main floor. We will be picking up the paint for the main floor today and if all goes well, we will be painting this weekend. Flooring will start going in the middle of next week and then we will get the electricians back to do the final install of outlets, switches and fixtures.
Cabinets for the kitchen will arrive today sometime. We plan on putting them on the front porch until the painting is done. They could be installed early next week. Plumbing will be next. Getting closer to "move in" day. I ordered the cabinets for the Laundry room and work room yesterday. Those shoould arrive by early December.